SUCCESSFUL CRANE LIFT OF 30-METRE-BRIDGE ACROSS WALLENDBEEN RAIL CORRIDOR
Friday, 15 October 2021 A 750-tonne crane has successfully lifted a 30-metre long, four-metre wide steel bridge over the rail corridor and into place along Burley Griffin Way at Wallendbeen. Member for Cootamundra Steph Cooke said the placement of the temporary road over the rail bridge was planned down to the finest detail. “We have had crews working locally to connect the 210 pieces of the bridge since June,” Ms Cooke said. “They’ve faced challenges with wet weather and

Steph Cooke MP
Oct 14, 2021
WORK CONTINUES ON TEMPORARY BRIDGE AT WALLENDBEEN
Thursday, 9 September 2021 Work is continuing on the construction of a temporary bridge on Burley Griffin Way at Wallendbeen to restore this critical connection for road users as quickly as possible. Member for Cootamundra Steph Cooke said a 62-tonne piling rig has driven in steel in-ground supports for the placement of the 210-piece temporary bridge. “Crews have faced prolonged wet weather and found soft ground conditions on site to be less than ideal, requiring an addit

Steph Cooke MP
Sep 9, 2021
WORK CONTINUES ON TEMPORARY BRIDGE AT WALLENDBEEN
Monday, 30 August 2021 Work is continuing on the construction of a temporary bridge on Burley Griffin Way at Wallendbeen to restore this critical connection for road users as quickly as possible. Member for Cootamundra Steph Cooke said every effort was being made to open the temporary bridge to traffic as soon as possible. “We understand the significant impact the 40-minute detour is having on the community, motorists and freight operators,” Ms Cooke said. “We want to assure

Steph Cooke MP
Aug 30, 2021
THE 210-PIECE BRIDGE CHALLENGE STARTS AT WALLENDBEEN
Tuesday, 6 July 2021 Work to construct a temporary bridge at Wallendbeen to speed up the opening of Burley Griffin Way for local residents and freight operators, is now underway. Member for Cootamundra Steph Cooke said the bridge installation is an engineering challenge and is comprised of modular, pre-engineered steel parts, which are being connected on site over the next three months. “The bridge is being transported from Sydney to Wallendbeen in 210 pieces and will be a

Steph Cooke MP
Jul 6, 2021
WALLENDBEEN BRIDGE SOLUTION IN SIGHT
Thursday, 17 June 2021 Work will start next week to build a temporary crossing to replace the demolished road over rail bridge at Wallendbeen, saving drivers a 40-minute detour. Member for Cootamundra Steph Cooke said the replacement crossing of the rail corridor along Burley Griffin Way at Wallendbeen was required after the overbridge was damaged by heavy rain in March and needed to be demolished. “We are conscious of how much extra travel time is required to divert arou

Steph Cooke MP
Jun 17, 2021
TEMPORARY BRIDGE TO RESTORE ACCESS AT WALLENDBEEN
Tuesday, 18 May 2021 The Burley Griffin Way will be reopened in the coming months with a temporary bridge to be built over the rail line at Wallendbeen. Local drivers are currently undertaking a 40-minute detour following the demolition of the old bridge after it was heavily damaged by rain. Member for Cootamundra Steph Cooke said the bridge would provide temporary access to Burley Griffin Way while a permanent solution is planned and built. “Since the rail bridge was dem

Steph Cooke MP
May 18, 2021
SAFETY IMPROVEMENTS ON THE WAY FOR BURLEY GRIFFIN WAY AT STOCKINBINGAL
22 February 2018 Member for Cootamundra Steph Cooke has announced road safety will soon be improved on Burley Griffin Way at Stockinbingal with a number of upgrades to take place from later this month. Ms Cooke says the NSW Government has allocated $1.95 million to repair and strengthen a section of Burley Griffin Way at Stockinbingal, about 45 kilometres west of Harden. “The project will significantly improve safety at this location where there is a high incidence of reporte

Steph Cooke MP
Feb 21, 2018